docs(tests): pass-2 P3 follow-ups from PR #265 (policy clauses, #238/#240 reconciliation) #271

Open
opened 2026-10-03 18:01:08 +00:00 by gabogg · 0 comments
Owner

Follow-ups from review pass 2 of PR #265 (r54). None blocks Milestone 3, so this stays outside it.

  1. docs/architecture/agent-test-validation-policy.md drops three clauses that #217 decision record (comment 4305) marks confirmed:
    • D1 lists merge blockers as failed, pending or missing CI (policy says only failed or pending).
    • D9: a subset pass cannot certify the full suite.
    • D16: related open test issues are linked as examples, kept separate from what the research PR delivered.
  2. Policy line 6 is about 120 columns wide; the rest of the file wraps at about 80.
  3. The policy references should list #238 and #240 once their briefs are reconciled. That reconciliation is a P2 in PR #218's pass-2 review, so #218 owns it, not this issue.

Acceptance criteria

  • The policy states D1, D9 and D16 in full.
  • Policy line 6 is rewrapped.
  • The policy references list #238 and #240.
Follow-ups from review pass 2 of PR #265 (r54). None blocks Milestone 3, so this stays outside it. 1. `docs/architecture/agent-test-validation-policy.md` drops three clauses that #217 decision record (comment 4305) marks confirmed: - D1 lists merge blockers as failed, pending **or missing** CI (policy says only failed or pending). - D9: a subset pass cannot certify the full suite. - D16: related open test issues are linked as examples, kept separate from what the research PR delivered. 2. Policy line 6 is about 120 columns wide; the rest of the file wraps at about 80. 3. The policy references should list #238 and #240 once their briefs are reconciled. That reconciliation is a P2 in PR #218's pass-2 review, so #218 owns it, not this issue. ## Acceptance criteria - [ ] The policy states D1, D9 and D16 in full. - [ ] Policy line 6 is rewrapped. - [ ] The policy references list #238 and #240.
Sign in to join this conversation.
No milestone
No project
No assignees
1 participant
Notifications
Due date
The due date is invalid or out of range. Please use the format "yyyy-mm-dd".

No due date set.

Dependencies

No dependencies set

Reference
gabogg/hikcentral#271
No description provided.